INSTRUCTIONS FOR APPLYING
CEDAR PLUS CEDAR SHINGLES
AS A CLASS "C" OR "B" ROOF COVERING
Class "C" or "B" labeled red cedar shingles may be applied over open spaced or solid sheathing.
Roof Pitch and Exposure
Proper weather exposure is important, and depends largely on roof slope. On roof slopes of 4" rise in 12" horizontal run (pitch 1/6) and steeper, the standard exposures are: S" for 1/6" shingles; 5½" for 18" shingles; and 7½" for 24" shingles. On roof slopes less than 4/12 to a minimum of 3/12, reduced exposures are recommended.
Roof Application
Shingles normally are applied in straight, single courses. Shingles must be doubled at all eaves. Butts of first-course shingles should project 1½" beyond the first sheathing board. Spacing between adjacent shingles (joints) should be ¼". Joints in any one course should be separated not less than 1½' from joints in adjacent courses, and joints in alternate courses should not be in direct alignment.
Fasteners
Hot dipped zinc coated nails or stainless steel staples are recommended. However, any U.B.C. approved corrosion-resistant fasteners can be used. Apply each shingle with two (only) fasteners. Each fastener should be placed not more than ¾" from the side edge of the shingle and not more than 1" above the exposure line. Use 3d (1¼") nails for 16" and 18" shingles, and 4d (½") for 24" shingles. In all cases, fasteners should be long enough to penetrate at least ¾" or through the sheathing. Drive them flush, but not so that the head crushes the wood.
Valleys
The roof valley flashing shall be provided of not less than No. 28 gauge pre-painted baked enamel applied over an underlayment of not less than Type 15 felt. The metal shall extend at least 8 inches from the center line each way.
WARNING: Both raw and fire retardant treated Cedar products contain a level of tannic acid that can cause corrosion to unprotected metals and Concrete surfaces. Pre-painted galvanized or pre-painted aluminum gutters are recommended. Initial water runoff over both raw and fire retardant cedar can cause staining. A low pressure wash of the roof immediately after application recommended. Chemco is not responsible for any direct or indirect damages caused by water runoff
|